Domain 1: Land use and transportation relationships

Question 1

Two proposed station-area developments have identical residential density, land-use mix, parking prices, and rail service. Each is a quarter-mile from the platform in a straight line. One has a direct, accessible sidewalk connection; the other requires a one-mile walk around a fenced highway interchange. A forecast assigns identical transit shares using density and straight-line station distance. What assumption most needs revision?

Show answer & explanation

Correct answer: A - Transit access cost should reflect the usable walking route, not just straight-line proximity.

Domain 2: Needs assessment for short- and long-range planning

Question 2

A regional four-step travel model reproduces independently estimated zonal trip productions, zonal trip attractions, and regional mode shares. Its origin-destination table nevertheless sends too many suburban residents to downtown jobs and too few to suburban employment centers when compared with an independent travel survey. Which model stage is failing this validation check?

Show answer & explanation

Correct answer: D - Trip distribution: allocating trips between origin and destination zones.

Question 3

An employment district is changing from office uses to warehousing and distribution, while its forecast total employment remains unchanged. A modeler proposes retaining the existing commercial-vehicle trip estimate because the number of jobs is unchanged. Before accepting that estimate, the planner should:

Show answer & explanation

Correct answer: B - Disaggregate employment by industry and revise freight-trip assumptions for the changed economic activities.

Domain 3: Transportation system planning for short- and long-range goals

Question 4

A bus-lane pilot is intended to increase peak-direction traveler throughput. Before the pilot, a screenline carried 1,200 cars per hour averaging 1.25 occupants and 20 buses per hour averaging 40 passengers. During the pilot, it carries 1,000 cars per hour at the same occupancy and 30 buses per hour averaging 50 passengers. Walking and cycling volumes are unchanged, and all adopted safety, accessibility, and vehicle-delay limits are met. Which finding should govern the pilot decision?

Show answer & explanation

Correct answer: B - Retain the pilot: total car-occupant and bus-passenger throughput increased by 450 people per hour.

Question 5

A county's rural mobility study has held open houses in the county seat and received many requests for commuter express service. Residents without cars and residents unable to travel to the meetings were largely absent; local service organizations report unmet trips from outlying communities. Alternatives have not yet been selected. Which change would make the engagement program more responsive to those missing perspectives?

Show answer & explanation

Correct answer: A - Arrange accessible outreach through local service organizations and use the findings to revise the alternatives.

Domain 4: Transportation system evaluation

Question 6

A corridor's travel-time dashboard reports the following for comparable weekday periods. Previously, mean travel time was 30 minutes, the 95th-percentile time was 45 minutes, and the buffer index was 50%. Now, the corresponding values are 40 minutes, 52 minutes, and 30%. A manager interprets the lower buffer index as evidence that travelers can budget less total time for 95% of trips. Which interpretation is defensible?

Show answer & explanation

Correct answer: C - The proportional buffer has decreased, but the travel time needed to cover 95% of trips has increased.

Question 7

Two mutually exclusive corridor alternatives have already been evaluated against the same no-build baseline in present-value dollars. Alternative A has $8 million in costs and $20 million in benefits. Alternative B has $14 million in costs and $30 million in benefits. Both are affordable, use the same analysis period, and have no material nonmonetized differences. The objective is the greatest monetized net benefit. Which recommendation correctly applies incremental benefit-cost analysis?

Show answer & explanation

Correct answer: A - Select B: the incremental benefit-cost ratio is approximately 1.67, supporting the higher investment.

Domain 5: Public policy

Question 8

Under a highway availability-payment public-private partnership, the private partner finances, builds, and maintains the facility. The public agency collects tolls and owes contractual availability payments regardless of traffic volume, with deductions only for specified performance failures. The facility meets those performance standards, but toll revenue falls below forecast. Under this arrangement, who bears the toll-revenue shortfall?

Show answer & explanation

Correct answer: C - The public agency, because its availability-payment obligations remain due when toll receipts fall.

Domain 6: Environmental analysis

Question 9

A federally assisted roadway project would use a narrow strip of a significant, publicly owned park and permanently remove its only accessible entrance. The design provides no replacement access. The sponsor proposes a Section 4(f) de minimis impact finding because less than 1% of the park's acreage would be acquired. Which conclusion should guide the environmental review?

Show answer & explanation

Correct answer: C - Loss of usable park access prevents a de minimis finding for the design as proposed.

Domain 7: Plan implementation

Question 10

During a construction inspection, a planner sees wheelchair users entering a live traffic lane because work has blocked the only accessible sidewalk. No protected detour is available. Unrelated work farther along the corridor can continue without affecting pedestrian access. The project manager asks for an immediate recommendation. The planner should recommend that the contractor:

Show answer & explanation

Correct answer: D - Pause the operation blocking access and restore a protected, accessible pedestrian route before that operation resumes.